Wednesday, December 3, 2008

Still Avoiding Sanding

I've been finding every possible job to tackle in the powder room taht doesn't involve sanding the walls - pretty sad for such a small room! But I'm about to the point where I just need to get it over with. The trimwork is all but complete now except for casing which is yet to be made. The caps for the wainscotting is finished, just a simple piece with a bead routered. The sill for the window is in place....same bead detail.



I went ahead and installed the metal crown for the tin ceiling too. To give myself a nailer and added support for these flimsy pieces, I ripped some square stock and installed on the wall and ceiling where the crown sits. This worked out really well.
On the corners, the first piece goes flat and then you have to trace out the profile cut for the other side to meet it. It made up a respectable corner.





Not much else getting done these days on the house while catching up on working my wood pile for the winter - about 2 cords left to split.

Sunday, November 23, 2008

Interior Season Begins

Finally - back to normal work schedule again and I can put the old work belt back on at home. With one minor snow fall already and the wood stove already roaring on a daily basis, my scaffolding season is over and it's time to get back to some inside projects. The plan this winter is to get the powder room and kitchen done so we can finally start living like "normal" people again - you know the one's with kitchen's on the first floor and stuff. The workout from carrying groceries up to the second floor maybe healthy, but it's getting REALLY OLD!

It's probably been a year and a half since I touched this room. Just to recap, the plumbing and wiring are done, beadboard is installed, and tin ceiling is up minus the crown pieces. Drywall is hung with two coats of mud already done. I did build a jamb earlier this year that's waiting for a door to be installed.

I managed to do some prep work during the rare free time I've had recently. The powder room, which I originally planned to do the floor in tile, will now be an oak floor. I have 500 sq. ft. of oak that I removed from the first floor, so I figured heck, that would make a nice floor in the powder the room.... and it's free. So I ran some through the planer lightly just to clean it up. I also started stripping a door for this room which takes a good bit of time.

After laying down some rosin paper, I started laying the floor from the back wall. Once past the pipes it was pretty easy work.



Once I'm done the messy work I'll give it a sanding to blend the boards a bit. Then I may go with a golden oak stain and poly.

Next is trimming out the wainscotting. I'm using a 1x6 base plus capping. The vertical pieces are 1x3 and 1x2's with an overlap - giving 2 inches reveal at the corners. Top piece is a smaller casing molding which eventually will get a cap piece which I'm still contemplating on design. Probably will be a simple piece with the bead edge that's common in the woodwork of the house.







Once this trimwork is done, I need to finish the drywall mudding. I couldn't get myself to sand just yet, so I picked something a little more fun first - even if it's a bit out of order for what I should be doing....

Sunday, November 2, 2008

Didn't Quite Make It

It's that time of year again where I put in 60+ hours a week at work and I fill the piggy bank back up for the up and coming projects.....



And outside work season is pretty much done. It's dark when I get home and getting borderline too cold too paint. Things will return to normal after Thanksgiving and it will then be back to inside work. That will be a nice change of pace since the siding project is starting to get OLD!



I managed to get shakes installed around to the first side window and the soffit installed around the corner. I still haven't installed the weather head on the service yet, but will get that done before winter. The two big front windows were also installed which came out nice and tight - so now all the front windows have been replaced. Two panes shattered while taking one window out but we won't get into that! Fortunately no cuts....



I cleaned out the powder room of fixtures and tub in prep to finish it. I only have one coat of mudding left and the should be ready to start paint and final trim. It's getting close to the point where I'll need to make some new casing to match the original in order to do powder room and kitchen. I think I'm going to set up in the kitchen where its not so cold. Plus I have the suction system now to keep dust under control. I never did this before so I figured I would practice on new pine till I get the hang of it. The I try to tackle some oak for the rest of the downstairs. These two projects should consume most of the winter till spring - then I can FINALLY finish the outside work.


WAY TO GO PHILLIES!!!!!

Tuesday, October 14, 2008

Electric Service Remount

As talked about before, the bracket for my electric drop appeared to have ripped out at some point and reattached - but not to a stud. Tearing off the layers of siding revealed just how poorly attached it was. I removed the siding except what was under the bracket and then started hanging the new siding. Once I was sided up to the next nearest stud towards the front of the house, I was able to make the switch to a new bracket.


old bracket


I pre-drilled and threaded in the new reinforced ceramic bracket. Next I hooked on a new tension clip to the bracket. Then laying the bracket on the guide cable (also the neutral wire for the service drop) I slid in the tapered mating piece. As tension is applied to the bracket, the pulls the taper closer making a tighter grip to the cable. It's a simple and really reliable design. Once the new mounting was complete I was able to remove the old bracket and the siding underneath it. Fair warning though, extreme caution needs to be taken when working around a service. One bad move can leave you a toasty critter and there is no breaker out on the street lines to blow if you do short something out! Usually the wire, the tool, or you will become the failing point to break the circuit if something bad happens.






I still need to put a service weather head on the cable. Right now it just has a "gooseneck" head, where they just bend the cable over to keep water from getting in the cable where the sheathing is cut to expose the individual leads. A weather head has a mounting screw and keeps the top of your cable more secure.

Sunday, October 5, 2008

Running Out Of Time

My work schedule gets crazy again starting Oct 25th, so basically I have till then to get as much done on this side as I can. After that it will be pretty much dark when I get home (and probably won't feel like doing much!). The corner is stripped down and papered, plus the belt trim is stripped - so now I can start to shingle the corner and get the front finished. I started yesterday and have three rows done up to the porch roof along the side. The next level will start wrapping around the front. I have a few batches done so we'll see how far I get today, but the limiting factor on time again will be how fast I can get more batches painted....



I ran into a problem with the service cable. It appears that at some point in the past it was ripped off the house and then remounted about 6 inches away. The problem is they didn't his a stud! As I started prying hoping to work some of the siding out from behind it and be able to leave it in place - the entire bracket started moving - yikes. So I just worked around it for now leaving it everything in place. The sheathing is pretty thick, but with all the material between the bracket and the sheathing I don't think it grabbed to much wood. So my electrician buddy told me a trick to switch the triplex (wires coming from the pole) to a new bracket without having take on the full weight of it. It's a good 100 feet run to the pole, so I doubt I'd be able to hold on very long let alone try to fish onto a new bracket. I get into this more when I actually do it.
Another issue I had to finally deal with was a 1 1/2 inch conduit run that went from the service panel, up the outside wall along the service cable, then down along the belt trim and poke into the house in the from bedroom and the back bedroom/2nd floor kitchen. There were 5 circuits total which had to be disconnected from the main panel and pulled back to where they went back into the house on the second floor. Then I was able to remove all the ugly conduit. Two circuits were dedicated to outlets probably for window AC units, so I just eliminated them. Three others feed the third floor which was semi redone before I bought the house. Two of these seemed to power most of what I'm using up there, so I temporarily made a junction box in the front bedroom and powered these two a new feed I ran to power the front bedrooms. When these rooms are gutted I can run the lines up to the third floor and to the closet where the central AC will be and a sub panel.

Sunday, September 28, 2008

Finally Back

Before leaving for vacation, I was able to finish up the soffit around the corner, add the crown detail, and do final painting. It's tied things together pretty well.





Back from vacation I built scaffolding around the corner so I can make my way around the final side of the house. Once again another colony was nested in the soffit which made for a fun tear down. It's a little more tricky here with the electric service which would not mix well with aluminum siding if I nicked a wire! The old soffit and aluminum tear down is finished, so next will be getting the old shakes down and working the corner with new - if the weather cooperates. I think we brought the English weather back with us.....




And just to make you all feel better about your own "not square" homes - check out "The Crooked House of Windsor". The pic doesn't do justice for just how crooked this house was!


Saturday, September 6, 2008

3rd Floor Unveiling

Well..... Here it is! Got the scaffold down just in time for tropical storm Hanna's arrival.




Now it's back to finish up the 2nd floor.

Wednesday, September 3, 2008

Enjoy The View While It Lasts

It won't be long now before I come back down to "safer" heights....




Over the past week I managed to get all the stripping done, repaired the window sill and trim, finished all the shingles and beadboard - basically you can stick a fork in it except for the finish painting. That should be complete tomorrow. The bead board I've been using so far once again worked good in this application. Once I caulked everything in, it tied together great.




Hopefully the scaffolding will be down by the weekend and I can really appreciate the work.

Tuesday, August 26, 2008

More Pics - And More Progress

As promised - a few more detailed pics of work written about in previous post.


The reproduction windows

New crown flares out starter course for 3rd story

New composite bead board sistered over original

Today I installed the drip edge and fitted the crown molding. It was a bit tough sneaking it under the shingles, but with the help of a pry bar I managed. The crown was another challenge working with 12 foot pieces by myself. I ended up cracking one before deciding to just temporarily screw in place to get fitted, then predrill and nail when it's all fitted in place. I'll just have to fill a few holes - no biggie. The crown really cleans up this section and now its ready for final paint. I do need to sneak in one more row just before the shingles run up the rafter. Checking my photos of the originals, they ran these rows closer to the transition than I thought.



Drip edge and crown installed along roof line

Monday, August 25, 2008

3rd Story Progress

This weekend with some help from John I managed to get a good jump on the 3rd floor work. While I started rebuilding the crown that flares out the shingles on this level, John removed the pair of replacement double hung windows and prepped for the installation of the reproduction set. With the crown rebuilt I added the starter course and finished papering the sheathing in prep for the siding.

Next the bead board had to be dealt with in the "inset" area. I decided to go with the same material I've been using to replace the soffit. On the inital vertical sections I just mounted them right over the original since the new pieces are only a 1/4 inch thick. Once it starts the 45 degree angle under the roof I nailed 1x3 boards to use as a nailer and this will let them sit flat since nails are popping through from the asphalt shingles above. The beadboard can't be installed here yet until I strip the front rafters.

Back on the windows, they were made almost dead on perfect and just had to be tweaked because the opening were a little out of square. Once installed and opening freely, the next day John fabricated a new sill to match the originals. This he made from the pine bases I replaced under the radiators on the first floor. Finally stops were added with built in weather stripping. Brass hardware is on backorder at the moment. There is still an issue of making a screen - but I'll get into that later.



Next day I started installing the shingles on the outer section, getting as far as running up the rafters. I was sure to document how the old timers made the transitions, since there was a bit of thought and a few shingle hanging tricks that went into them (using thinner pieces, cutting layers at certain spots, etc).




Today I got the nerve to do the upper peak. I had an eyelet mounted to a piece of angle that my dad made for his roof job, and I was able to mount that to the house just above the double windows. I hooked my lanyard to this from my body harness I have from work - giving me just a little security.... especially up on a step latter on the top section of scaffold! Next step will be rebuilding the trim along the roof line, then the outer section can be finished painted. I'll take some better and more detailed pics this week.



Outer shingles finished

Sunday, August 24, 2008

Advanced Scaffold Building




Tuesday with the help of my buddy John, we managed to get the scaffolding built on top of the porch roof to access the 3rd floor front dormer. I played with a few ideas for the base, usually over complicating the matter...... but in the end, the adjustable feet had just enough to make it level. The upper feet I just used wedges. For the lower, I mounted to a 2x6 - which one edge rested on the roof and the other end was propped up with a 2x3. This made for a level base to fasten to. The bottom feet are also supported by 2x4's that run along the roof. I'll take a closeup later and add to this post. It's quite high up there for sure - but still not as bad as the chimney job!








All the woodwork up here has seen better days

Quite a view - about 45 feet from street level!

Saturday, August 16, 2008

Next Section Preview

I managed to get up to the third floor section and strip some aluminum siding to reveal the original shingles. It should look unique when finished, I've never seen a front like it. I plan on building at least one level of scaffold across the porch roof to work on it which I'm still kicking around some ideas in my head for supporting it. I might do a second level in the middle, but after working on the ladder, I think I could use a step ladder to reach the middle no problem.The rest should all be within easy reach since the planks should end up just where the third floor starts.



The middle section is starting to take shape and hopefully a few more batches should get it completed.



Here are the two windows that will go in the third floor. All the dormers originally had these style windows and will eventually be done with reproductions of the original design. The craftsman that made the windows for the foyer window seat made these for me and did a heck of a job. This time at least he had a sample to work with, which was removed from the house and used to fill a busted window in the garage.


You can see the originals in a closeup from a picture taken around 1940. I still can't believe how lucky I was to find all the original photos I have - what a big help they've been!


Tuesday, August 12, 2008

Second Side Wrap-Up

FINALLY - the second side is totally finished with the siding and soffit. The end result looks fantastic and was worth the endless hours of painting shingles. But, I still have a long way to go.




I've already done a third of the front, which gives me a jump on the third side. In between some wicked storms this weekend I managed to get the center section stripped, flashed, and papered and then today I installed the starter and first course. Now it's back to making more batches of shingles again.....




I pretty much finished landscaping the driveway side as well complete with birdbath, sundial, and Rach added a gnome for good measure! There's at least 15 different plants along here which should really take shape next year. All I need to do still is add some sand and set the slate pavers permanently.



Wednesday, August 6, 2008

Sweating Along

It's been pretty consistent near or in the 90's for several weeks now, which making for slow progress. This side is just about wrapping up and I should hopefully have the scaffold down by the end of the week after some final painting. To finish the soffit, once again I had to add bracing between the rafter tails and add a nailer along the wall. I had one rafter end that was so bad it needed to be sistered on each side in order to support the soffit and crown fascia. Other than that it was more of the same.





I think after the front I may finish the front 3rd floor peak before moving to the last side. I got the 2 windows for the 3rd floor last week which came out really nice. I'll post some pics next time. This is the dude who made the pair for the foyer window seat. The other 5 dormer windows will be made next winter since I won't be tackling them till next year.